How to debug the cement concrete batching plant

How to debug the cement concrete batching plant

1 Overview

In all electric concrete batching plant equipment installation, wiring and electrical control system and after the completion of the unit owners and suppliers of the person concerned after examination recognized by the mechanical and electrical and other relevant personnel to debug. Trial is to confirm the installation was successful, and the electronic control system wiring is correct, performance, and economic and technical indicators electromechanical equipment meets the requirements of the contract.

2. Preparation before test

2.1 All mechanical equipment should be related to the specification requirements for inspection and lubrication filling oil gear, rotated by hand if necessary, to ensure safety.

2.2 confirm that all electrical connections meet the requirements of the drawings, the wiring is correct, grounded. Confirmed that the supply voltage to meet the requirements.

2.3 Verify that the system air pressure is greater than 0.6Mpa, compressed air is dry and clean, and open the tank drain valve deflated sewage. 0.7Mpa air line to seal the pressure test, check all joints for leaks and promptly eliminated. After the air line pressure test, blowing pipe, oil mist filling 10 oil.

2.4 confirmation mixers, screw machine, tape machines, combined aggregate hoppers, aggregate storage, powder silos, water tanks, additives, etc. inside the box clean and free of debris.

3. No-load test

3.1 on the power switch and power button on the console and check the power supply is normal, check the emergency stop button is effective and reliable early warning signal, ready to load debugging.

3.2 itemized test each device to start and stop the motor (with scene buttons and console buttons to start and stop), check the motor rotation direction is correct; especially the twin-shaft mixer, to pay attention to its two electric motors turn, should be separately start confirming its motor after turning right before the merge starts. No-load running for 15 minutes, check the operating conditions and the degree of heat bearing.

3.3 itemized solenoid valves manual test button and the console button pneumatic actuator member (including arc gate, butterfly valves, ball valves, etc.) action is correct. Action should be no obstruction, creeping phenomenon. Pneumatic adjustment element group lubricator drip flow to ensure smooth operation of pneumatic components.

3.4 Check and adjust the limit switch, proximity switch operation correctness.

3.5 Adjustment nine hopper level, and to ensure that the door is closed tight arc, proximity switch on the cylinder. Said admixture to adjust the level of the bucket, to ensure verticality sensors. Static school scale: the computer is set in the state school scales with weights by one school scale and recorded, calculate static accuracy. Static accuracy of ± 0.1%, does not exceed ± 0.2%.

3.6 mixer idling test: no confirmation within twin-shaft concrete mixer miscellaneous foreign body after the first start of concentrated oil pump mixer bearing grease, and then start the mixer motor to run for 30 minutes and the normal operation, the stirring blade cylinder wall clearance is adjusted to <3 mm. (See mixers Instructions)

3.7 Check screw conveyor without confirmation miscellaneous foreign objects, one by one start screw conveyor, running 15 minutes without exception.

3.8 Start the tape machine, when feeder starts operation, the tape may not deviation, if any deviation adjustable rear tension bolts and self-aligning roller. It runs 15 minutes without exception.

3.9 No-load linkage test: computer manual and automatic mixing plant load linkage test systems, test equipment startup sequence is correct, the equipment and body movements are normal. Adjustment is completed, all of the mechanical linkage should be eight hours running-load test.

4. Overload test

In the no-load commissioning confirmed after passing system forms the basis of concrete on the material can be overloaded on test and production test. Overload test and production test can be combined.

5. Microcomputer function tests

In accordance with the computer operation manual for the upper and lower computer features one by one test, check the check print a single print or modify a single format.

6. The concrete test specimen

Concrete samples ultimate performance is affected by many factors, only as a reference test sample mobile mini concrete batching plant trials.

7. The test organization and test report

Test organizational unit by the owner, design units and technical support, the parties concerned in close cooperation. After passing the test performance, the parties sign the test report. professional concrete batching plant allowed into official use.